Project location
Bishop Auckland, County Durham
Client
Bishop Auckland College
Architect
Howarth Litchfield Partnership
Referee
Client representative’s full name
Mr Malcolm Cresswell
Position on project
Estates manager
Full contact address
Bishop Auckland College
Woodhouse Lane
Bishop Auckland
County Durham
DL14 6JZ
Telephone number
01388 443000
Fax number
01388 443002
Email address
malcolm.cresswell@bacoll.ac.uk
Cost consultants
Faithful+ Gould
Main contractor
Surgo Construction
M&E contractor(s)
H Malone, Veale Nixon
Other key supply-chain partners
Harry Marsh, Wyn, SRS.
Overall project value
£28,500,000.
Brief description of works
First phase was major extension to provide new teaching facilities. Demolition of existing buildings allowed phase two to proceed. College operational throughout the contract period.
Works to phase one were completed 10 weeks early.
Project procured under a two stage process, operating on an open book basis.
Environmental features
Full building management system for energy use. Grey water harvesting system. Passive ventilation. ‘Green’ specification.
Subcontract arrangements
Variety of standard ‘Egan compliant’ forms with back to back conditions relating to the main contract.
Completion date
Phase one 2007
Phases two and three 2010.